UHP LANCING CLEANING FOR SHELL AND TUBE HEAT EXCHANGERS – BLNG SHUTDOWN 2018 – BRUNEI

UHP LANCING & CLEANING FOR SHELL & TUBE HEAT EXCHANGER – BLNG SHUTDOWN 2018 December

Flow Synergy Technics Sdn Bhd, was awarded by ADININ & WORKS ENGINEERING SDN BHD (AWE) – Brunei on December 2018. Scope to provision Ultra High Pressure machine 4 units complete with accessories, UHP self rotating bunchie nozzles to cater ID 16mm. To provide experienced blasters 18pax on day & night shift  to manage the shutdown with 2 experienced supervisors. Full time safety (SSS) coordinator 1 pax. Planning & execution engineer 1 pax. Job was carried out 24hours as rotating shift.

Equipment involved :

  1. E3318-A, 2. E3318-B, 3. E3318-C, 4. E3318-D, 5. E3318-E, 6.E3318F & 7.E3319
  2. Total tubes involved 18924nos (straight tubes) Sus material
  3. Od 19.05mm x 9.15mtrs x 2.11thickness

Duration took about 4days max to lance all internal tubes till 100% clean to bare metal. Inspection method, Boroscope & visual. After proper house keeping and internal inspection with BLNG & AWE personnel job successfully hand over. No LTA was encountered while the job progress.

After successful completion all team was demob back to Johor Work shop.