GLYCOL LINE 3” DUPLEX & 1” 2” CARBON STEEL REPAIR & MODIFICATION ONBOARD SK 316 NC3 GAS FIELD – OFFSHORE
FLOW SYNERGY TECHNICS SDN BHD : WAS AWARDED A FEED (FRONT & END ENGINEERING DESIGN) GLYCOL DUPLEX & CARBON STEEL LINE’S( 3”, 2” & 1”) ONBOARD SK 316 NC 3 GAS FIELD by TMJV
ONSHORE FABRICATION :
Deluge nozzle modification
- To provision proper repair procedure adhere to obtain an approval for repair as per original provided drawing as mentioned. To provision qualified CUNI 90/10 AWS welder at site (onshore) to weld and to renew the new nozzles as provided by TMJV and to braised the old material before installation – 26 joints
Glycol leakage line repair & modification
- To fabricate the newly provided pipes based on the P&Id by qualified 6G welder and fitter to weld by mean to provide all related welding machine, consumables, tools. To ensure competent welder to handle A312/316 Stainless steel material with weld process GTAW
- Pipe dimension : 3″ TP 316 sus x minimum 4 weld supports / with NDT inspection on welding seams – DPI
Glycol Recirculation Line fabrication
- To fabricate the newly provided pipes based on P&Id by qualified 6G welder and fitter to handle A106 carbon steel material with weld process GTAW
- Pipe dimension : 1″ & 2″ Carbon steel
- 3-GL-95817-91412 – 412mm x 6Joints
- 3-GL-95818-11412 – 13286mm x 15Joints
- 3-GL-95818-11412 –5451/924mm x 17Joints
- 3-GL-95818-91412 – 413mm x 6Joints\
- After fabrication process the external surface will be blasted with SA2.5 standard finish coated with FST provided weather resistance PU coating – Joton
OFFSHORE INSTALLATION :
- SUS 3″ LINE
- To field weld extra length for considering pipe length site adjustment, to modify pipe support and to weld new L type support on the secondary structure fabrication the pipe spools. To perform the fabrication & installation on board of Sk316 at offshore to adhere with proper Boiset & medical certs.
- Welding done by Habitat close measure welding method with tech
- CS 1″ & 2″ falnge to flange installation and to weld pipe support
Job successfully hand over to owner (PCSB) & client (TMJV) after proper inspection on board SK 316 NC 3 field on 18.11.16. Max 11 crew was onboard for the said project
 
				