SHUTDOWN 2017 STATIC EQUIPMENT CLEANING – EVYAP SABUN SDN BHD
Flow Synergy Technics Sdn Bhd was awarded static equipment HPWJ cleaning and mechanical work for EVYAP SABUN SHUTDOWN 2017 DOSH INSPECTION.
The maintenance scope covered :
- To provision qualified technician, 12 blaster and machineries 4 units of UHP diesel driven machine @ 30000 psi and 15000psi pump to lancing and cleaning c/w cross jet & polishing nozzles to remove the scaling 100%
- Dismantle & refit all related end cover to ease the cleaning operation
- After proper housekeeping & inspection to box back and hand over
1.0 Fractionation plant
(Tube internal lancing) – 4160 tubes – 15 KPSI
- Feed Preheater x 3 units x 701 tubes
- Cooler x 10units x 2315 tubes
- Feed exchanger x 3units x 372 tubes
- Steam Generator x 3units x 372 tubes
- Condenser x 2 units x 200tubes
- Cold trap x 5 units x 200tubes
(Washing + Flushing ) – 25units
- Column x 5units – washing
- Evaporator x 7units – washing, open overhead & bottom flushing
- Light tank x 1unit – Flushing
- Flash vessel x 11units – Washing & flushing
- Air receiver x 1unit – washing
2.0 Hydrogenation plant
(Tube internal lancing ) – 1063tubes
- Cooler x 2 units x 397 tubes (30KPSI)
- Preheater x 1unit x 110tubes (15KPSI)
- Exchanger x 4 units x 400tubes
- Condenser x 2 units x 156tubes
(Washing + Flushing ) – 7units
- Drier x 1unit – washing
- Reactor x 1unit – washing
- Tank x 3unit – washing
- Vessel x 2units – washing
The 10500 men hours shutdown was successfully handed over on the estimated schedule within 24hrs rotation shift. upon leak testing and final by DOSH & IRISH inspection the plant shutdown was handed over successfully .